AG Report: 7 Mind Boggling & Costly Weaknesses Found
Table of Contents
- 1. The Sultanah Nora Ismail Hospital upgrading project
- 2. Millions in tax evasion
- 3. Technical errors in CBU vehicles assessment
- 4. National Defence Education Centre Development project
- 5. East Coast not given priority in flood mitigation projects
- 6. Low-income earners did not get the rice subsidy
- 7. 39 civil servants were living rent-free
The third series of the 2014 Auditor-General’s report is finally out. After much publicity on how much money was loss, and how many projects mismanaged from the last series, what news does this latest report bring?
According to the report, a deficit of RM37.35 billion (3.49% GDP) was incurred by the federal government last year
Loans amounting to RM109.08 billion were taken internally and externally to cover the deficit, repay existing debts and finance the Housing Loan Trust Fund.
The federal government received revenue totalling RM220.63 billion in 2014, up RM7.26 billion (3.4%) from the RM213.37 billion it recorded in 2013.
Unsurprisingly, this series of the report found more instances where taxpayers’ money was unnecessarily wasted due to poor management and transparency.
Here are some of the findings released by the report that could have you palming your face the rest of the day:
1. The Sultanah Nora Ismail Hospital upgrading project
Ministry of Health
The latest report by the AG found that the contractor, Sejagat Bakti, in charge of the upgrading project of the Sultanah Nora Ismail Hospital in Batu Pahat, Johor, was appointed through direct negotiations and was given the fast-track by the Finance Ministry. Furthermore, the company has had no history of working on hospital or medical facilities prior to the appointment.
The project was grossly delayed, plagued with a long list of non-compliance issues, with 4,198 complaints lodged during the Defects Liability Period (DLP) that were not addressed completely by the contractor.
Contractors and vendors who are unable to meet projects deadline are typically imposed Liquidated and Ascertained Damages (LAD), and in the case of Sejagat Bakti, the Works Ministry clarified that the contractor had applied for a second extension after the initial 90 days but this was rejected and LAD was to be imposed.
However, the Finance Ministry approved the LAD exemption for Sejagat Bakti on July 3 2015.
2. Millions in tax evasion
Ministry of Finance
The audit was carried out between November 2014 and February 2015, found that tax collection has increased in 2014 by 8.7% (RM305.72 million) compared to 2013 (RM309.63 million).
However, the audit also found 1,383 individual taxpayers with business income, involved in more than 5,900 cases, have evaded tax amounting to RM44.03 million last year.
Of the taxpayers found evading tax, 1,351 taxpayers owed a total of RM26.32 million for more than two years, with the amounts ranging from RM20.08 to RM945,347.
The Inland Revenue Board (LHDN) also failed to take action to prevent the taxpayers, involved in 802 cases of tax evasion with tax arrears of over RM25 million, from leaving the country.
3. Technical errors in CBU vehicles assessment
Ministry of Finance
The spotlight was on the Customs Department in the third series of the AG report, as technical errors in completely built up (CBU) vehicles assessment left almost RM15 million in taxes uncollected.
The Malaysian Association of Malay Vehicle Importers and Traders (Pekema) was found fail to apply for time extension to keep their unsold imported vehicles more than 36 months without being taxed.
Estimated duty from those unsold imported vehicles came up to RM12.65 million, as at December 31, 2014, which makes up the bulk of the uncollected taxes amount. Other issues found include:
- 29 million in taxes was under-collected due to errors found in 213 K1 forms from an audit sample of 3,931 forms.
- The same mistakes have also led to an over-collection of RM499,296.
- Seven audited licensed warehouses with 725 vehicles in total with an estimated duty of RM38.22 million were uninsured for fire and theft.
- The monitoring of vehicles from/to Designated Area was deemed unsatisfactory due to the lack of comprehensive and immediate measures to penalise offenders who, for example, forfeit bank guarantees.
4. National Defence Education Centre Development project
Ministry of Defence
The Ministry of Defence (MinDef) was tasked to oversee the National Defence Education Centre (NDEC) development project, which consists of the Malaysian Armed Forces Staff College (MAFSC) and the Malaysia Armed Forces Defence College (MAFDC). These two colleges aim to provide the requisite training facilities for three military services (Air Force/Navy/Army) to the highest level in the military field.
However, the AG report found the management of NDEC less than satisfactory due to the following weaknesses:
- The project was delayed for 282 days as of July 29 due to the contractor’s poor performance.
- A devaluation of land value caused the Government to bear the project cost at RM26.87 million.
- The contractor, Awan Megah Sdn. Bhd. (AMSB) was late in submitting its Performance Bond of RM4.95 million.
5. East Coast not given priority in flood mitigation projects
Ministry of Natural Resources & Environment
Under the Tenth Malaysia Plan, the Flood Mitigation Projects (FMP) was implemented across Malaysia, which consist of river improvement works, construction of pump house and other related facilities, upgrading of pond detention, raising the river bund as well as land acquisition.
The audit carried out from December 2014 to April 2015 found that all audited projects were delayed, where one to six Extension of Time (EOT) were approved, due to delays in land acquisition, obstacles and problems on site, weather conditions, changes in design to adapt to current site condition and delays in connection of electricity.
Some of the components and works carried were also found not to comply with specification and do not meet quality standard.
Although, generally, the FMP has reduced the risk due to flood such as loss of human lives and property damages, states like Kelantan and Terengganu with the largest flood area and highest average losses caused by flood, were not given priority to the implementation of FMP.
6. Low-income earners did not get the rice subsidy
Ministry of Agriculture and Agro-based Industry
Instead of benefitting its target group, the low-income Malaysians, the subsidised rice went to foreigners, restaurants and food stalls, and pets.
The programme, approved in 2008, started with the aim of covering the losses incurred by BERNAS (the nation’s sole rice distributor) to procure and distribute ST15% and S15% rice as well as to ensure targeted low income group are able to buy quality rice at controlled prices.
However, the audit, conducted between March and July 2015, found that 38 out of the 83 grocery shops did not have subsidised rice in stock because they did not receive enough supply to meet demand.
From the 86 consumers who responded, 54 were Malaysians, while the rest were those who were not eligible for subsidised rice, consisting of foreigners from Bangladesh, Nepal, Indonesia, Pakistan and Philippines, as well as restaurant operators who use the rice as pet food.
It was also found that quotas were given to wholesalers with expired licences, and wholesalers who failed to carry out wholesaling activities.
In response to the report, the Ministry of Agriculture and Agro-based Industry (MOA) announced that it had abolished the subsidy for the Super Tempatan 15% broken (ST15) grade rice in Nov 1, 2015, following too much leakage in the programme.
7. 39 civil servants were living rent-free
Prime Minister’s Office
Under the Property Management Division, the audit found some weaknesses in the management of quarters for civil servants.
There were 39 civil servants that were living rent-free in these quarters, where the rental was not deducted from their salary, costing the Government RM811,326. More than 600 tenants were identified as at April 2015 with rent arrears amounting to RM3.58 million due to tenant’s transfer, resignation and dismissal.
A total of 575 unoccupied units were also not promptly allocated after completion of maintenance work, and RM88,787 worth in rent arrears were incurred by tenants from Non-Governmental Organisations (NGOs).
Over the past few years, the Malaysian government has made some progress toward better management of its assets and also the taxpayers’ money, but as evidently shown in the latest AG report, more work needs to be done, and better transparency needs to be in place.
Rather than nit-picking on each of the above weaknesses highlighted by the AG, the government needs to look at the bigger picture and see how it can better implement effective mechanisms to ensure good activities that benefit the rakyat (such as the rice subsidy programme) can be better implemented. The sense of ownership in each programme needs to start from the individual implementing it in the grass roots.
Money mismanagement can happen to everyone. Keep track of your spending with the right credit card!